Phase: Two

Architect: Huckabee

Construction Manager: Pogue  Construction

Start Construction: Winter 2016
Finish: Spring 2018*
*Dates are projections and subject to change.


Project Fact Sheet | Spanish

Construction Photos

Multipurpose Activity Center Photos

Bid Notice

Project Status: In Construction

Construction of the addition is ongoing. The addition will house a ninth-grade wing, along with a new kitchen and dining area. The current cafeteria and dining area will be converted into classrooms, including new science labs and art rooms.

The Multipurpose Activity Center, a separate project at Sam Houston, is complete.


Project Scope

  • Build Multipurpose Activity Center (separate project - see construction photos)
  • Upgrade technology connectivity
  • Identify and improve existing site accessibility
  • Add additional card access controls
  • Repair/replace and upgrade heating and A/C, electric, plumbing, exterior, interior finishes, landscaping, parking and roof
  • Renovate existing fine arts, career/technical and athletics spaces
  • Add new 9th grade center • Add new cafeteria and kitchen
  • Repurpose existing cafeteria/kitchen space for classrooms, science labs and art rooms
  • Upgrade security cameras (to be done by AISD security department)

This report includes highlights of projects. The list is not comprehensive and is subject to modification.