Thornton Elementary

Information and Links:

Address: 2301 East Park Row Drive  Arlington, TX 76010

Phase: Two

Architect: Huckabee

Construction Manager: Sedalco  Construction Services

Start Construction: Summer 2017*
Finish: Summer 2018*
*Dates are projections and subject to change.


Project Fact Sheet | Spanish

Construction Photos

Bid Notice

Project Status: In Construction

Construction started in May 2017.


Project Scope

  • Add 2 STEM labs
  • Add strings classroom
  • Upgrade technology connectivity
  • Identify and improve existing site accessibility
  • Add secure entry vestibule
  • Replace roof
  • Add ADA parking and resurface existing parking lot
  • Repair/replace and upgrade electrical, electrical equipment, heating and A/C, plumbing interior finishes, exterior, landscaping, playground and site lighting
  • Add additional card access controls
  • Replace K-pod (kindergarten building) heating and A/C, flooring and roof
  • Upgrade security cameras and PA system (to be done by AISD security and technology departments)

This report includes highlights of projects. The list is not comprehensive and is subject to modification.