Information and Links:
Address: 4900 W. Arkansas Ln. Arlington, TX 76016
PROJECT DETAILS
Phase: Four
Architect: LBL Architects
Construction Manager: Ratcliff Constructors
Start Construction: Fall 2018
Finish: Summer 2019
Project Status: Substantially Complete
Construction began in November 2018 with demolition. The building was completely redone to make it ready for the new school, which opened for the beginning of the 2019-2020 school year.
Project Scope
- The Arlington ISD will open a second early college high school located in the building that formerly housed Venture High School. The 2014 Bond is funding construction to renovate and repurpose the building. Learn more about the Early College High School.