PROJECT DETAILS
Phase:
Two

Architect: KAI Texas

Construction Manager: Pogue  Construction

Start Construction: Spring 2017
Finish: Fall 2018*
*Dates are projections and subject to change.


 

Project Status: Complete

Construction began in the spring 2017 and is complete, including the STEM lab addition, new front-entrance security vestibule, renovated reception and renovated music and strings rooms. A retaining wall at the front of the property is complete and landscaping is finished.


Project Scope

  • Build addition for 2 STEM labs
  • Add strings classroom
  • Upgrade technology connectivity (new fiber)
  • Improve existing site accessibility
  • Replace parking
  • Add secure entry vestibule
  • Add additional card access controls
  • Repair/replace and upgrade electrical equipment, landscaping, heating and A/C, playground, plumbing, interior finishes, PA system and site lighting
  • Repair rooftop hatch for access
  • Replace K-pod (kindergarten building) heating and A/C, flooring and roof
  • Upgrade security cameras and PA system (to be done by AISD security and technology departments)