Information and Links:

Address: 3000 South Fielder  Arlington, TX 76015



LIFECYCLE/DEFICIENCY WORK

Phase:
Three

Architect: Corgan

Construction Manager: Big Sky  Construction

Start Construction: Winter 2018
Finish: Fall 2018*
*Dates are projections and subject to change.



TRACK CONSTRUCTION

Phase: Three

Architect: Stantec

Construction Manager: Hellas Construction

Start Construction: Spring 2018
Finish: Fall 2018*
*Dates are projections and subject to change.


Project Status: Substantially Complete

Work at Gunn has wrapped up. Concrete edging for new landscaping in front of the building was installed last spring break. A new ramp to the stage is complete. Electrical work - installing new circuits and wiring for the addition of new battery backup emergency fixtures throughout the building - is done. The parking lots and drive have been demolished and redone. Renovations in the science labs are done, and new RTUs have been installed. Gunn also received a new fire alarm system. In addition, several collaboration areas were created within the building by removing old locker banks and installing new white boards.

Construction of the new four-lane track started in March and is substantially complete.


Project Scope

  • Upgrade technology connectivity (new fiber)
  • Improve existing site accessibility
  • Add additional card access controls
  • Replace and add parking
  • Replace sections of roof
  • Repair/replace and upgrade heating and A/C, electrical, electrical equipment, plumbing, fire alarms and landscaping
  • Add new 4-lane track (separate project)

This report includes highlights of projects. The list is not comprehensive and is subject to modification.