Johns Elementary

Information and Links:

Address: 1900 Sherry Street  Arlington, TX 76010



PROJECT DETAILS
Phase:
Three

Architect: LBL Architects

Construction Manager: Phillips/May Corporation

Start Construction: Spring 2018
Finish: Fall 2018*
*Dates are projections and subject to change.


 

Project Status: In Construction

Construction started in April. The first task is demolition in the future strings room.

A separate project, the replacement of HVAC equipment and replacement of the kitchen freezer/cooler is complete.


Project Scope

  • Replace HVAC (separate project managed by Infinity Contractors)
  • Replace kitchen freezer/cooler (separate project managed by Mart, Inc.)
  • Add two STEM labs
  • Add strings classroom
  • Add secure entry vestibule
  • Upgrade technology connectivity
  • Improve existing site accessibility
  • Replace roof
  • Resurface parking lot
  • Add additional card access controls
  • Repair/replace and upgrade electrical equipment, heating and A/C, fire alarms, plumbing, interior finishes, exterior, structure, landscaping, site drainage and site lighting
  • Replace K-pod (kindergarten building) heating and A/C, flooring and roof
  • Upgrade security cameras and PA system (to be done by AISD security and technology departments)
  • Replace HVAC system

This report includes highlights of projects. The list is not comprehensive and is subject to modification.