Crow Construction Photos
Project Status
UPDATE: Walls for the new gymnasium are up and roofing is set to begin. For the new classroom wing, the steel is standing and the roof is decked. Framing the exterior walls is about to begin. The steel is also standing for the kitchen addition. Nearby, the new detention pond is complete and fenced, and the new parking lot is complete.
The new spaces and renovations are slated for completion by August of 2021. At that time, Crow’s student population will grow as part of an east Arlington master plan that will rezone the entire area, replace Berry and Thornton Elementary schools with new, bigger buildings and close Knox and Roark Elementary schools.
Project Scope
- Kitchen Replacement and Renovations
- Heating & A/C, Electrical, Plumbing Improvements
- Interior Renovations (Paint, flooring, ceilings, lighting, etc.)
- ADA Accessibility Improvements (Door hardware, ramps, restrooms, etc.)
- Restroom Renovations
- Site Improvements (Lighting, landscaping, drainage, irrigation, signage, etc.)
- Roof Renovations
- Paving Improvements
This list is not comprehensive and is subject to change.
- Full-day Pre-K Renovations Specific to Campus Needs
- Gymnasium Replacement
- Playground Replacements and Renovations (Surface, equipment, canopy, ADA accessible)
- Instruments
This list is not comprehensive and is subject to change.
- Expanded Security Camera Coverage and Upgraded Camera Software
- Safety & Security Enhancements (Exterior and interior key system upgrades, district communication system upgrades, lighting, fencing, etc.)
- Device Upgrades and Expanded Access
This list is not comprehensive and is subject to change.
PHASE
Phase 1
CONSTRUCTION
Start: Summer 2020 Finish: Fall 2021
ARCHITECT
Corgan
CONSTRUCTION MANAGER
RJM Contractors
PHASE
Phase 1
CONSTRUCTION
Start: Fall 2020 Finish: Spring 2021
ENGINEER
Glenn Engineering
CONSTRUCTION MANAGER
Reeder Concrete Inc. (concrete flatwork)
Miracle Recreation Equipment (playground equipment and install)