Crow Leadership Academy

Crow Leadership Academy
1201 Coke Dr. Arlington, TX 76010

Status

Design and construction update
     

Scope

Scope of work planned
for the campus
   

DETAILS

Phase, schedule,
architect and
construction manager

Questions

Questions
about Crow?
Contact us.

Project Status

  • Addition Design
    0%
  • Addition Construction
    0%
  • Playground Design
    0%
  • Playground Construction
    0%

UPDATE: Walls for the new gymnasium are up and roofing is set to begin. For the new classroom wing, the steel is standing and the roof is decked. Framing the exterior walls is about to begin. The steel is also standing for the kitchen addition. Nearby, the new detention pond is complete and fenced, and the new parking lot is complete. 

The new spaces and renovations are slated for completion by August of 2021. At that time, Crow’s student population will grow as part of an east Arlington master plan that will rezone the entire area, replace Berry and Thornton Elementary schools with new, bigger buildings and close Knox and Roark Elementary schools.

Project Scope

  • Kitchen Replacement and Renovations
  • Heating & A/C, Electrical, Plumbing Improvements
  • Interior Renovations (Paint, flooring, ceilings, lighting, etc.)
  • ADA Accessibility Improvements (Door hardware, ramps, restrooms, etc.)
  • Restroom Renovations
  • Site Improvements (Lighting, landscaping, drainage, irrigation, signage, etc.)
  • Roof Renovations
  • Paving Improvements

This list is not comprehensive and is subject to change.

  • Full-day Pre-K Renovations Specific to Campus Needs
  • Gymnasium Replacement
  • Playground Replacements and Renovations (Surface, equipment, canopy, ADA accessible)
  • Instruments

This list is not comprehensive and is subject to change.

  • Expanded Security Camera Coverage and Upgraded Camera Software
  • Safety & Security Enhancements (Exterior and interior key system upgrades, district communication system upgrades, lighting, fencing, etc.)
  • Device Upgrades and Expanded Access

This list is not comprehensive and is subject to change.

Project Details

PHASE
Phase 1

CONSTRUCTION
Start: Summer 2020      Finish: Fall 2021

ARCHITECT
Corgan

CONSTRUCTION MANAGER
RJM Contractors

PHASE
Phase 1

CONSTRUCTION
Start: Fall 2020     Finish: Spring 2021

ENGINEER
Glenn Engineering

CONSTRUCTION MANAGER
Reeder Concrete Inc. (concrete flatwork) 
Miracle Recreation Equipment (playground equipment and install)

Contact Us

Bond 2019 logo
AISD Bond 2019 logo

Bond 2019

$966 MILLION

• Facilities
• Fine Arts
• Safety, Security & Technology
• Transportation

Fine Arts icon
Fine Arts icon

Fine Arts

The fine arts portion includes: theater equipment and black boxes, instruments, visual arts equipment and work surfaces, piano replacements and uniforms for marching bands, drill teams and choirs.

Icon for safety, security and technology
Icon for the Bond 2019's Safety, Security & Technology

Safety, Security & Tech

The safety, security and technology portion includes: additional security cameras and upgraded alarm systems, districtwide communications system upgrade, network infrastructure, device replacements and strategic 1:1 (student devices).

Transportation icon
Transportation icon

Transportation

The transportation portion of the bond includes new buses, shuttle buses, service vehicles. Also included are new vehicles and trailers for the Dan Dipert Career + Technical Center, the Agricultural Science Center, high school bands and security.

Facilities icon
Facilities icon

Facilties

The facilities portion includes: new construction, condition needs and life cycle improvements for all schools, new playgrounds at all elementary schools and facility upgrades for fine arts and athletics.