CVPA Resources
- Project Fact Sheet
- Schematic Design Presentation (10.5.17)
- Groundbreaking Photos
- Construction Photos
- Aerial Construction Photos
Information and Links:
Address: 900 E. Sanford St. Arlington, TX 76011
PROJECT DETAILS
Phase: Three
Architect: HKS Architects
Construction Manager: Adolfson & Peterson
Start Construction: Fall 2018
Finish: Fall 2020*
*Dates are projections and subject to change.
TIME-LAPSE CONSTRUCTION VIDEOS
2.8.19-2.22.19
1.28.19-2.8.19
1.14.19-2.1.19
1.7.19-1.22.19
12.5.18-1.11.19
1.7.19-11.14.19
1.7.19-2.6.19
1.7.19-3.2.20
1.7.19-3.17.20
Project Status: Open
The AISD hosted a groundbreaking ceremony Sept. 13, 2018, to kick off construction (see photos), and groundwork began the last week of September 2018 (see photos). The building opened for students in January 2021.
Project Scope
The districtwide fine arts center will serve the entire district, grades prekindergarten-12, with world-class performance and demonstration venues, along with classroom and gallery space.
- 1,250-seat concert hall
- 425-seat theater
- Classroom space
- Art and dance studios
- Instrument repair center
- Gallery space
This report includes highlights. The list is not comprehensive and is subject to modification.