Bids

PHASE 1  |  PHASE 2  |  PHASE 3  |  PHASE 4  |  PHASE 5

Subcontractors and suppliers interested in bidding for jobs related to the AISD 2014 Bond package need to bid directly through the construction managers. If bidding is open for a project, click on "OPEN" next to the project name below to find out more information. For more information about the scope of a project, click on the project's name.

The AISD encourages local, small and HUB businesses to bid for district projects. If you are a local, small or HUB vendor and have any questions about working with the AISD, please call 682-867-7352 or email tcraig1@aisd.net.

PHASE 1

Project
Bidding
CM

Start
Work

Finish
Work
Ferguson Education Center (Venture; Newcomer) Closed Pogue 6/2015 1/2016
Ousley Junior High Closed Pogue 6/2015 9/2016
Workman Junior High Closed Pogue 5/2015 1/2017
Jones Academy Closed Joeris 6/2016 7/2017
Corey Academy Closed Pogue 11/2015 1/2017
Boles Junior High Closed Pogue 7/2016 9/2017
Peach Elementary Closed Balfour Beatty 6/2015 1/2017
McNutt Elementary Closed Balfour Beatty 6/2015 1/2017
Career and Technical Center Closed Balfour Beatty 2/2016 8/2017
Multi-purpose Activity Centers Closed Balfour Beatty 9/2015 1/2017
Professional Development Center Closed Pogue 9/2016 3/2017

PHASE 2

Project
Bidding
CM
Start
Work
Finish
Work
7 Elementaries: Anderson, Beckham, Blanton, Burgin, Hale, Remynse and West Closed WB Kibler 10/2016 7/2017
7 Elementaries: Ashworth, Bryant, Crow, Ditto, Kooken, Larson and Pearcy Closed WB Kibler 10/2016 9/2017
Farrell and Starrett Elementaries Closed WB Kibler 11/2016 TBD
Foster, Moore and Wood Elementaries Closed Pogue 3/2017 9/2017
Bebensee, Duff, Fitzgerald and Williams Elementaries Closed Imperial 2/2017 12/2017
Nichols and Turning Point Junior Highs; Ellis and Sherrod Elementaries Closed Balfour Beatty 1/2017 8/2017
Arlington High School; Morton and South Davis Elementaries Closed - 11/2017 TBD
Martin High School; Little and Miller Elementaries Closed Balfour Beatty 8/2016 8/2017
Sam Houston High School Closed Pogue 1/2017 8/2017
Crouch, Knox and Thornton Elementaries Closed Sedalco 6/2017 3/2018
Agricultural Science Center Closed Ratcliff 2/2017 7/2017

PHASE 3

Project
Bidding
CM
Start
Work
Finish
Work
CMARs for Phase 3 projects (and Sam Houston High School) Closed
Johns and Goodman Elementaries: HVAC replacement Closed Infinity 10/2016 8/2017
Johns and Webb Elementaries: Kitchen renovations Closed Infinity 11/2016 7/2017
Johns and Goodman Elementaries: Deficiency/Life-cycle Closed - 11/2017 8/2018
Lamar High School: Culinary lab renovation Closed Hutcherson 10/2016 3/2017
Butler Elementary Closed - 11/2017 8/2018
Dunn Elementary Closed Imperial 5/2017 5/2018
Hill and Swift Elementaries Closed BRW 10/2017 8/2018
Amos and Atherton Elementaries Closed Pete Durant & Assoc. 5/2017 5/2018
Gunn Junior High; Key and Short Elementaries Closed Pogue 11/2017 8/2018
Seguin High School Closed Pogue 7/2017 6/2018
Berry, Rankin and Roark Elementaries Closed VLK 11/2017 8/2018
Pope, Speer, Webb and Wimbish Elementaries Closed BRW 10/2017 10/2018
Fine Arts Center 5/2018  HKS 11/2018 6/2020
Junior high schools - track and lighting TBD TBD TBD TBD

PHASE 4

Project
Bidding
CM
Start
Work
Finish
Work
 Architectural Services Phase 4  Closed
Bowie High School
Lamar High School
Bailey Junior High
Boles Junior High
Carter Junior High
Ashworth Elementary
Blanton Elementary
Crow Elementary
Kooken Education Center
Larson Elementary
Athletics Complex 5/2018

PHASE 5

Project
Bidding
CM
Start
Work
Finish
Work
 Architectural Services for Phase 5 Closed