Information and Links:

Address: 1001 E. Division St. Arlington, TX 76011



PROJECT DETAILS
Phase:
Four

Architect: HKS Architects

Construction Manager: Adolfson & Peterson

Start Construction: Fall 2018
Finish: Fall 2020*
*Dates are projections and subject to change.



TIME-LAPSE CONSTRUCTION VIDEOS

2.8.19-2.22.19
1.28.19-2.8.19
1.14.19-2.1.19
1.7.19-1.22.19
12.5.18-1.11.19
1.7.19-2.6.20
1.7.19-3.2.20
1.7.19-3.17.20

Project Status: Open

The Arlington ISD hosted a groundbreaking ceremony Sept. 13, 2018, to kick off construction (see photos), and groundwork started soon after (see photos). Construction is now wrapping up. The pool opened in October 2020 and the arena opened in November 2020.

Watch a construction tour from June 2020 and see the pool filling up with water.


Project Scope

The districtwide athletics complex will provide competition and practice venues for sports lacking adequate space at high school campuses. It will include venues for:

  • Swimming and diving, including competition and water safety training
  • Competition Wrestling
  • Basketball and Volleyball
  • Elementary Gymnastics