Turning Point Secondary School

Turning Point Secondary School

Information and Links:

Address: 2209 North Davis Drive  Arlington, TX 76012



PROJECT DETAILS
Phase:
Two

Architect: WRA Architects

Construction Manager: Balfour  Beatty

Start Construction: Spring 2017
Finish: Fall 2017


 

Project Status: Substantially Complete

Bond-funded projects at Turning Point are nearly complete. Access control upgrades need to be completed and then the project will be closed out.


Project Scope

  • Paint exterior CMU walls
  • Replace exhaust fans and wash stations in science labs
  • Upgrade technology connectivity (new fiber)
  • Improve existing site accessibility
  • Add additional card access controls
  • Replace roof
  • Add electrical outlets
  • Replace HVAC
  • Replace fire alarm system
  • Upgrade sidewalks
  • Upgrade security cameras (to be done by AISD security department)

This report includes highlights of projects. The list is not comprehensive and is subject to modification.