Short Elementary

Information and Links:

Address: 2000 California Lane  Arlington, TX 76015



PROJECT DETAILS
Phase:
Three

Architect: Corgan

Construction Manager: Big Sky  Construction

Start Construction: Winter 2018
Finish: Fall 2018*
*Dates are projections and subject to change.


 

Project Status: In Construction

Construction of the new STEM labs is ongoing and millwork has been installed. Mechanical upgrades in the school are also in process. New roof-top units were installed over spring break.


Project Scope

  • Add 2 STEM labs
  • Add strings classroom
  • Add secure entry vestibule
  • Upgrade technology connectivity (new fiber)
  • Improve existing site accessibility
  • Replace portions of roof
  • Add additional card access controls
  • Repair and upgrade electrical equipment, heating and A/C, fire alarms, plumbing, interior finishes, and landscaping
  • Replace K-pod (kindergarten building) flooring, roof and heating and A/C
  • Upgrade security cameras and PA system (to be done by AISD security and technology departments)

This report includes highlights of projects. The list is not comprehensive and is subject to modification.