Seguin High School

Information and Links:

Address: 7001 Silo Road
Arlington TX 76002



PROJECT DETAILS
Phase:
Three

Architect: Stantec

Construction Manager: Pogue  Construction

Start Construction: Summer 2017*
Finish: Fall 2018*
*Dates are projections and subject to change.


 

Project Status: In Construction

Work on the classroom addition is ongoing with most of the exterior work complete. Inside, much of the tile wainscot is in, along with light fixtures and ceiling grid. Inside the existing building, a number of renovation projects are underway now that school is out, including renovations in the culinary lab and several athletics spaces.

The new Multipurpose Activity Center at Seguin, a separate project, is already complete.


Project Scope

  • Build Multipurpose Activity Center (separate project - see construction photos)
  • Build classroom addition
  • Upgrade fine arts spaces
  • Upgrade technology connectivity
  • Identify and improve existing site accessibility
  • Upgrade existing athletic dressing facilities
  • Add additional card access controls
  • Upgrade security cameras (by AISD security department)
  • Repair/replace and upgrade heating and A/C, plumbing, interior finishes, exterior and landscaping

This report includes highlights of projects. The list is not comprehensive and is subject to modification.