Atherton Elementary

Information and Links:

Address: 2101 Overbrook Drive  Arlington, TX 76014



PROJECT DETAILS
Phase:
Three

Architect: Perkins + Will

Construction Manager: Pete Durant  & Associates

Start Construction: Fall 2017
Finish: Summer 2018*
*Dates are projections and subject to change.


 

Project Status: In Construction

Work in the STEM labs is nearly complete. The strings room is finished and now work will start in the music room. Outside, roofing is ongoing. Over spring break, three storage rooms received new flooring, along with the conference room and K-pod. One or two additional electrical outlets were also installed in every classroom. The outlets will be tied in over the summer when additional electrical infrastructure improvements are made. Work in the summer will also include sidewalk replacement at the front of the school, among other projects.


Project Scope

  • Add two STEM labs
  • Add strings classroom
  • Add secure entry vestibule
  • Upgrade technology connectivity
  • Improve and identify existing site accessibility
  • Replace roof
  • Add additional card access controls
  • Repair and upgrade electrical equipment, heating and A/C, fire and safety, plumbing, interior finishes, landscaping and site lighting
  • Replace K-pod (kindergarten building) flooring, roof and heating and A/C
  • Upgrade security cameras and PA system (to be done by AISD security and technology departments)

This report includes highlights of projects. The list is not comprehensive and is subject to modification.