Blanton Elementary

Blanton Elementary

Information and Links:

Address: 1900 South Collins Street  Arlington, TX 76010



STEM, STRINGS & VESTIBULE
Phase: Two

Architect: Hahnfeld Hoffer Standford

Construction Manager: W.B. Kibler

Start Construction: Winter 2016
Finish: Summer 2017



LIFECYCLE & DEFICIENCY
Phase: Four

Architect: VLK Architects

Construction Manager: Reeder General Contractors Inc.

Start Construction: Fall 2018*
Finish: Summer 2019*
*Dates are projections and subject to change.


 

Project Status: Sub. Complete/In Design

Construction for the first of two bond projects at Blanton - the two new STEM labs, strings room and security vestibule - is substantially complete. The closeout process is underway.

The second bond project - the lifecycle and deficiency scope - was approved by the AISD Board of Trustees on Oct. 4, and construction is scheduled to begin in early 2019.


Project Scope

Bond-funded work at Anderson is being done in two stages. The first stage includes adding two STEM labs, a strings room and security vestibule. The second stage includes a number of life-cycle and deficiency upgrades.

  • Add two STEM labs
  • Add strings classroom
  • Add secure entry vestibule
  • Upgrade technology connectivity
  • Improve existing site accessibility
  • Add additional card access controls
  • Replace roof
  • Repair/replace and upgrade heating and A/C, electrical, interior finishes, plumbing, exterior, playground and landscaping
  • Repair and add parking
  • Replace K-pod (kindergarten building) heating and A/C, flooring and roof
  • Upgrade security cameras and PA system (to be done by AISD security and technology departments)

This report includes highlights of projects. The list is not comprehensive and is subject to modification.