Ousley Junior High held a faculty family night Aug. 11 to help kick off the new school year. The staff has grown considerably this year with the consolidation of Ferguson Junior High and Ousley on the Ousley campus. The evening, which included a cookout, gave the teachers a chance to meet each other and introduce…
Aug. 11, 2015 – The Citizens Bond Oversight Committee met August 10 to review progress the AISD has made implementing the 2014 Bond package. The committee heard updates from district leaders in each of the areas receiving bond funds: facilities, technology, fine arts, transportation and security. (Click here to see all the materials from the…
August 10, 2015 – AISD staff delivered, unloaded and set up desks and furniture in portable classrooms at Workman Junior High last week. The portable classrooms are temporary, brought in this summer to accommodate Workman’s growing student population. Once a new classroom addition on the south side of the existing building is completed in the…
August 6, 2015 – Rising seventh and eighth graders are attending a Lego robotics camp at Ousley Junior High this week. It’s one of the first opportunities for the newly consolidated students from Ferguson and Ousley Junior High schools to participate in an activity as one student body. Ferguson Junior High closed at the end…
August 4, 2015 – Workers used a crane to place new HVAC units on the roof at Ferguson Education Center this morning. New units are also being placed at Ousley Junior High this week. The new units, along with additional renovations and upgrades, are funded by the 2014 Bond package. For more details about the…
The Arlington ISD is accepting applications for positions on the Citizens Bond Oversight Committee. The committee is established to provide transparency and enhance public confidence in the use of proceeds from the sale of bonds authorized by Arlington ISD voters on May 10, 2014. The purpose of the committee is to provide findings and recommendations…
July 27, 2015 – AISD facility staff and contractors are undergoing training this week on e-Builder, a new software system purchased by the school district to assist with project management. It will prove especially helpful for the many facility projects related to the 2014 Bond package. All parties involved in the AISD’s capital projects, including…
The final day of the school year, June 5, 2015, was also the final day for “Hutch.” Now just a few weeks into the summer break, all the furniture, books, computers and school supplies are being moved out. The old, worn out school building is about to come down. The students who would have attended…
When the Ferguson Junior High students were released from school at noon on June 5, 2015, most were probably excited to start summer break. But for many of the teachers, it was a sad day. School is out for good. Ferguson Junior High is now closed. The brick junior high on Green Oaks Boulevard opened…
June 25, 2015 – The AISD and Pogue Construction hosted a prebid walkthrough meeting at Workman Junior High yesterday to allow potential subcontractors to see the building and ask questions about addition and renovation work scheduled to begin in mid-August. The projects, funded by the 2014 Bond package, are designed to support the growing student…