Short Playgrounds
Short Construction
Project Status
UPDATE: Construction started at Short Elementary over the summer and now is mostly finished. Work included significant interior renovations, including replacing the freezer/cooler and painting, flooring, exterior paving and roof improvements. New doors and hardware were installed in the spring. All work should wrap up over the summer.
New playgrounds for Short are also in phase three and are now open.
Project Scope
- Kitchen Replacement and Renovations
- Electrical and Plumbing Improvements
- Interior Renovations (Paint, flooring, ceilings, lighting, etc.)
- ADA Accessibility Improvements (Door hardware, ramps, restrooms, etc.)
- Restroom Renovations
- Site Improvements (Landscaping, irrigation, signage, etc.)
- Roof Renovations
- Paving Improvements
This list is not comprehensive and is subject to change.
- Full-day Pre-K Renovations Specific to Campus Needs
- Gymnasium Renovations
- Playground Replacements and Renovations (Surface, equipment, canopy, ADA accessible)
- Instruments
This list is not comprehensive and is subject to change.
- Expanded Security Camera Coverage and Upgraded Camera Software
- Safety & Security Enhancements (Exterior and interior key system upgrades, district communication system upgrades, lighting, fencing, etc.)
- Device Upgrades and Expanded Access
This list is not comprehensive and is subject to change.
PHASE
Phase 3
CONSTRUCTION
Start: Spring 2023 Finish: Summer 2024
ARCHITECT
Glenn | Partners
CONSTRUCTION MANAGER
Tegrity Contractors Inc.
PHASE
Phase 3
CONSTRUCTION DATES
Start: Summer 2023 Finish: Fall 2023
ENGINEER
Glenn Engineering
GENERAL CONTRACTOR
J Squared (concrete/earthwork)
Lea Park & Play (playground equipment and install)