Project Status
UPDATE: The Bond 2019 construction at Key Elementary is now complete, apart from a few punch list items. The old gym was demolished, and the new gym/storm shelter is now open. Renovations on the existing building are also complete, including a new fire alarm system, kitchen flooring, and renovations in the cafeteria and courtyard.
New playgrounds for Key were in phase three and are now open.
Project Scope
- Kitchen Renovations
- Heating & A/C, Electrical, Plumbing Improvements
- Interior Renovations (Flooring, ceilings, lighting, etc.)
- ADA Accessibility Improvements (Door hardware, ramps, restrooms, etc.)
- Restroom renovations
- Site Improvements (Lighting, landscaping, drainage, irrigation, signage, etc.)
- Paving Improvements
This list is not comprehensive and is subject to change.
- Full-day Pre-K Renovations Specific to Campus Needs
- Gym Replacement
- Playground Replacements and Renovations (Surface, equipment, canopy, ADA accessible)
- Instruments
This list is not comprehensive and is subject to change.
- Expanded Security Camera Coverage and Upgraded Camera Software
- Safety & Security Enhancements (Exterior and interior key system upgrades, district communication system upgrades, lighting, fencing, etc.)
- Device Upgrades and Expanded Access
This list is not comprehensive and is subject to change.
PHASE
Phase 3
CONSTRUCTION
Start: February 2024 Finish: Summer 2025
ARCHITECT
BRW Architects
CONSTRUCTION MANAGER
Hutcherson Construction
PHASE
Phase 3
CONSTRUCTION DATES
Start: Fall 2023 Finish: Fall 2023
ENGINEER
Glenn Engineering
GENERAL CONTRACTOR
J Squared (concrete/earthwork)
Lea Park & Play (playground equipment and install)